NewsNew England and Central-West Orana REZs in New South Wales, Australia, hit...

New England and Central-West Orana REZs in New South Wales, Australia, hit milestones

According to EnergyCo chief executive James Hay, the New England REZ is expected to attract more than AUS$24 billion (US$15.5 billion) in private investment by 2034, supporting over 6,000 construction jobs and 2,000 ongoing operational jobs.

The report outlines the infrastructure needed to connect the New England REZ with the existing electricity grid in the Upper Hunter and provides a preliminary analysis of matters to be assessed in an Environmental Impact Statement (EIS). This is expected to be finalised and placed on public exhibition in late 2025.

“The transmission infrastructure needed to deliver this includes two new 500 kilovolt (kV) transmission lines between Bayswater near Muswellbrook and the New England REZ, as well as a network of new 500kV and 330kV transmission lines and four new energy hubs within the zone,” Hay said.

New England REZ Executive project director Doug Parris added that the scoping report includes a preferred study corridor for the network infrastructure project, developed following ongoing consultation and field investigations since June 2023.

“The preferred study corridor is generally 1km wide and incorporates some narrower sections where co-location with existing infrastructure is proposed,” Parris said.

“Lodgement of the scoping report does not mean the corridor is finalised. EnergyCo will continue to work with landowners and undertake field studies to better understand constraints and opportunities for the transmission route. This is a critical step to refine the corridor further and find optimal locations for the transmission line easements, which will be up to 80 metres wide for each line.”

Central-West Orana REZ begins headroom assessment

Further south, the Central-West Orana REZ project has reached another milestone, with confirmation that EnergyCo has started the process of conducting a headroom assessment to increase the amount of aggregate maximum capacity that can connect in the REZ from 3GW to 6GW.

The headroom assessment is a technical process primarily designed to support generation and energy storage projects that are already working with EnergyCo and are covered by the Central-West Orana Renewable Energy Zone transmission project planning approval received in June 2024. 

The maximum capacity cap suggested in this headroom assessment may not be the final limit for the overall maximum capacity of the Central-West Orana REZ. EnergyCo said it will conduct future headroom assessments according to the Access Scheme Declaration.

Generators and storage projects aiming to connect to the Central-West Orana REZ are encouraged to engage with EnergyCo to discuss their access rights process. All generation and energy storage projects are subject to relevant planning and environmental approvals, including statutory consultation.

EnergyCo said that increasing the maximum capacity cap will help in making the Central-West Orana REZ successful for the New South Wales government, industry, host communities and energy consumers.

 » …

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Subscribe Today

GET EXCLUSIVE FULL ACCESS TO PREMIUM CONTENT

SUPPORT NONPROFIT JOURNALISM

EXPERT ANALYSIS OF AND EMERGING TRENDS IN CHILD WELFARE AND JUVENILE JUSTICE

TOPICAL VIDEO WEBINARS

Get unlimited access to our EXCLUSIVE Content and our archive of subscriber stories.

Exclusive content

Latest article

More article